Hi Bagghera
We have received credit twice for the site cost provisional sums. The amount was credited to the next progress payment. The actualisation of the PS will be done in numerous stages throughout construction until handover, depending on when the builder receives the invoice from the site work contractor. The difference between actual and provisional will be a variation and included in your next progress payment.
We've been told that we can request invoices if we want to.