Browse Forums Building A New House 1 Mar 10, 2010 11:14 pm I know this has been discussed before but was thinking of getting a poll so that it would be easier to look at what most did. If you can also say who did you use for the inspection. Oxford 22 @ Stage12a Point Cook Site Cut : 05/03/2010 Slab Pour : 24/03/2010 Frame Inspected : 06/04/2010 Pre-plaster Inspection: 22/04/2010 PCI: 16/07/2010 Final Inspection: 30/07/2010 Landscaping: who knows??? MyHomeoneThread Our Oxford22 Blog Re: 3rd Party Inspections 2Mar 11, 2010 7:01 am Used for the frame. Won't use for the lock-up... Probability of using one for the final inspection is about .45... So you might want to add another question: "experienced once, not sure will attempt again" ... built a Promenade with Clarendon. viewtopic.php?f=31&t=25104 20-10-09 - excavation and piering completed ... 12-04-10 - Basins fixed. Connecting to the electrical grid 23-04-10 - PCI 07-05-10 - HANDOVER! Re: 3rd Party Inspections 3Mar 11, 2010 7:49 am I selected 'Other Combination'. We are planning on using one at frame stage and handover stage. We have a house in Doreen. Built the PD Kensington 24 (with Alfresco & Rumpus option). We are in...Decorating in progress...pics to come soon... Re: 3rd Party Inspections 5Mar 13, 2010 8:53 pm Footing, Slab, Frame & Final. I am luck have a family member that works for a soil test & engineering firm so he inspected the footings, slab & frames and told me what problems to bring up with the builder. But I will pay for a hand over inspecton I am sure they will pick up on things I have missed. Cheers Lou http://take2-customdesigndownslope.blogspot.com 07-10-09 omg they have cut the block 14-05-10 we finally have the keys You have mandatory building inspections and privately engaged building inspections. The difference between the two comes down to inspecting the building so it's safe and… 3 18058 |