Can anyone help me out, I cant for the life of me remember what order things go in. (I dont think we paid that much attention last time!). I know some builders might do things in a slightly different order and it may depend on state but it would be helpful to know. I tried to search but nothing came up!
Also let me know if I have worded something wrong!
1. Site Cut
2. Pegging out
3. Foundations
4. Either boxing up or the bottom rows of bricks
5. Slab Pour
6. Frame work
7. Roof Trusses
8. Roof
9. Sarking
10. Bricking
11. Rendering and painting (if applicable)
11. Electrical, plumbing, ducted (anything) rough in
12. Plaster Hung
13. Setting
Have no idea what comes next... Just guessing - correct me
14. Painting?
15. Cabinets
16. Tiling?
17. Fit off of lights and plumbing fixtures
18. Decking
19. What else?