Browse Forums Building A New House Re: Building The floreat SPH aubin Grove 22Mar 10, 2010 9:58 pm Cooper's Build - Perth NOR viewtopic.php?f=31&t=30525 Prelim- mid Sept 2009, Pre Start 2 Feb, Siteworks- 21 April 2010, Slab- 10 May, Deliveries- all by 26 May Bricking- 28 May - 26 June, Roof complete 5 Aug, Float 28 Aug, Lock up 16 Sept Cabinets 1 Oct, Tiling 22 Oct, PCI 18 Nov, KEYS 3 Dec 2010 MOVED IN 17 DEC 2010 Re: Building The floreat SPH aubin Grove 25Mar 11, 2010 5:13 pm Building the Claremont with SPH viewtopic.php?f=31&t=28206 Earthworks 16/02 Slab 23/02 Drainer 26/02 Bricks 03/03 Brickies started 30/03 Brickie meeting 31/03 Tile meeting booked for 21/06 Paving started 29/07 1st PCI 29/07 2nd PCI 13/08 Handover 09/09 Re: Building The floreat SPH aubin Grove 28Mar 19, 2010 8:38 pm Cooper's Build - Perth NOR viewtopic.php?f=31&t=30525 Prelim- mid Sept 2009, Pre Start 2 Feb, Siteworks- 21 April 2010, Slab- 10 May, Deliveries- all by 26 May Bricking- 28 May - 26 June, Roof complete 5 Aug, Float 28 Aug, Lock up 16 Sept Cabinets 1 Oct, Tiling 22 Oct, PCI 18 Nov, KEYS 3 Dec 2010 MOVED IN 17 DEC 2010 go upvc window frames ensure insulation under colorbond. not just sarking, lighter color roof also not sure if you have seen this viewtopic.php?t=5823 last couple of pages… 4 110569 Even if it's not being sub-divided and you want to keep it as Torrens title, you will still need to talk to a town planner or Council themselves, to see if they will allow… 1 11035 |