Browse Forums Building A New House Re: Build Period 2Feb 04, 2010 12:16 pm Depends on soooo many things ie. how good your SS is at organising things, how much work his tradies have got on etc etc. I asked the same question of our builders a while back and got the following guide: Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Built a Tribeca 44 with the Big M Sales Accept 15/06/09, Contract Signed 24/09/09, Site Start 23/11/09, Slab 11/12/09, Frame 12/01/10, Roof 20/01/10, Lock-up 30/03/10, Fixing 30/04/10, Handover 27/08/10. Re: Build Period 3Feb 04, 2010 12:21 pm Hi Yellow It does depend on many things, below is the dates each stage has been completed on our build but this is a single story. We have been very lucky as hardly a day has passed with out tradies on site you need to understand the breakdown of warranties. 90 warranty is considered as minor defects rectification period where as the longer ones are more major/structural… 1 3819 Thank you so much everyone. This all makes a lot of sense. I guess when you talk to a builder who butters up everything to look very polished, you get to start believing… 8 2124 thank you! do we need to get this or our builder before we commence new build on the block? 2 4395 |