We are in the frustrating position of having to give 4 weeks notice on our rental and being unable to get a PCI or handover date for our house. I was hoping someone who has been through it all before can give us a guess of how long we have to go.
Our tiles have been completed this week, and next week we have the following booked in to be done:
- carpet installed
- shower screen/mirror/splashback installation
- painters coming back to finish the master bedroom and do some touch ups
- render painted.
As far as I can tell, the only things left to do are:
- staining the bifold doors
- another coat on the front door
- weather seals on all the doors
- plumbing fit off
- outdoor sensor lights to be installed
- shelves to be installed in pantry and cupboards
- appliances to be installed (day of handover I think?)
- cleaning
- inspections x 3 (big building supervisor, quality and our walkthrough) and associated fixes. I don't think anything major will come from this, us and our SS have been really happy with the quality of work done - the only things we have picked up is a few of the downpipes need to be dug down a bit more so we don't run over them with the lawnmower and some ******* bits of paintwork.
I don't know when any of that will happen because I forgot to ask last time I was talking to our SS.
Has anyone got any idea of how long I can expect? I am a bit concerned they won't give us a date until a week or two out then we are stuck paying rent on this house and not living here anymore!
Our house is about 26sq and with PD.