Browse Forums Building A New House 1 Jan 26, 2010 3:19 pm Hi all We are currently building with Hickinbotham. The brick work, tiles,electrical wiring, and gypock are all done. DH and I went to visit today and we realise they didnt raise our entry ceiling to 3m as per our contract. Is if worth asking them to fix this error or just ask for compensation??? We really dont want to delay the completion date. Unless the room is for storage then it's non compliant BCA V2 2019 S3 P3.8 You have 2 options 1. The builder deconstructs the section and rebuilds as per plan /… 7 10682 ok thanks - yes was wondering if that should have been listed as Option Three! 2 7741 I'll look into different shower heads and ask the plumber about some engineering and see what he says. Thanks 2 9563 |