Browse Forums Building A New House 1 Jan 12, 2010 4:22 pm Hi there, new to this, building a new home with Scott Park Homes south of the river We chose the Claremont plan from the Vittoria range with a few alterations. I will put this up when I can Had pre-start back in Nov, signed final plans in Dec, building license approved just b4 christmas. Now at the stage of earthworks scheduled for early Feb Building the Claremont with SPH viewtopic.php?f=31&t=28206 Earthworks 16/02 Slab 23/02 Drainer 26/02 Bricks 03/03 Brickies started 30/03 Brickie meeting 31/03 Tile meeting booked for 21/06 Paving started 29/07 1st PCI 29/07 2nd PCI 13/08 Handover 09/09 Re: Building With SPH - At Scheduling 2Jan 12, 2010 10:21 pm Bec2010 Hi there, new to this, building a new home with Scott Park Homes south of the river We chose the Claremont plan from the Vittoria range with a few alterations. I will put this up when I can Had pre-start back in Nov, signed final plans in Dec, building license approved just b4 christmas. Now at the stage of earthworks booked for early Feb So where abouts are you building? Nice to Have you aboard. I am building the Floreat South of the River. Had Pre Start end of October, went to scheduling on 8th December, but haven't heard when Earthworks are Building in Seville Grove Perth Floreat by Scott Park Homes Earthworks 16th February Thread https://forum.homeone.com.au/viewtopic.php?f=31&t=24936 Re: Building With SPH - At Scheduling 4Jan 12, 2010 10:42 pm Hi Bec and welcome! The Better Half and I have also built with SPH (our version of 'The Sovereign') and are just over a week away from moving in Don't be shy, if you have any questions - ask away. You'll find us SPH-ites all very easy going and quick to help. So .. what changes have you made? And, more importantly. Where are the pics? We lurve pics! Re: Building With SPH - At Scheduling 5Jan 13, 2010 4:19 pm Hi Unable to get to our plans at the moment, they are locked away, it was a good thing as I would have kept looking at them. Ill get to them soon though Original plan - http://www.scottparkhomes.com.au/Homes/ ... oorplan.pd Main changes we made - Double door entry, double shower in Ensuite and extended vanity, WC moved to the other side. Doors were added to Home Theatre, Home Office & WIL. Family & Alfresco now larger area as we took out the activity to have more open space Ok here are some of our colour selections ill put pics up soon Kitchen Bench top in Qstone ivory Doors in Laminex Licorice Linea, Pot drawers Formica (Silver Shadow) Ensuite Benchtop in Laminex Ashdust, Doors in Formica Asphalt 2nd Bathroom & Laundry Bench top in Laminex Platinum Micro, Doors in Stipple Cocoa Mr Gum I would say you should be at the same stage as us then. We did not receive a letter but I emailed our contact in contracts admin which is how we found out. Another email came back yesterday to say our file is with construction and we should hear within the next 2 weeks about time frames Two of you nearly moved in how exciting!! Building the Claremont with SPH viewtopic.php?f=31&t=28206 Earthworks 16/02 Slab 23/02 Drainer 26/02 Bricks 03/03 Brickies started 30/03 Brickie meeting 31/03 Tile meeting booked for 21/06 Paving started 29/07 1st PCI 29/07 2nd PCI 13/08 Handover 09/09 Re: Building With SPH - Colours 6Jan 15, 2010 10:37 am Hi guys, Here is a link to some of our internal colours, what do you think?, hope they look ok Ensuite Bench top http://www.laminex.com.au/resource/imag ... h_dust.jpg Doors http://www.formica.com.au/media/swatche ... sphalt.jpg Feature Mosaic Tile – Gemstone Galaxy http://i903.photobucket.com/albums/ac23 ... eature.jpg Floor Tile – Enviro Alloy http://i903.photobucket.com/albums/ac23 ... teTile.jpg 2nd Bathroom &Laundry Bench top http://www.laminex.com.au/resource/imag ... _micro.jpg Doors http://www.laminex.com.au/resource/imag ... _cocoa.jpg Floor Tile - Enviro Smoke Kitchen Bench top http://www.qstone.com.au/images/ivory5.jpg Doors http://www.laminex.com.au/resource/imag ... _linea.jpg http://www.formica.com.au/media/swatche ... Shadow.jpg Formica Silver Shadow used for Pot drawers & Kickboards Building in the Cockburn area of Perth WA Building the Claremont with SPH viewtopic.php?f=31&t=28206 Earthworks 16/02 Slab 23/02 Drainer 26/02 Bricks 03/03 Brickies started 30/03 Brickie meeting 31/03 Tile meeting booked for 21/06 Paving started 29/07 1st PCI 29/07 2nd PCI 13/08 Handover 09/09 Re: Building With SPH - Colours 7Jan 15, 2010 11:25 am Bec2010 Hi guys, Here is a link to some of our internal colours, what do you think?, hope they look ok Ensuite Bench top http://www.laminex.com.au/resource/imag ... h_dust.jpg Doors http://www.formica.com.au/media/swatche ... sphalt.jpg Feature Mosaic Tile – Gemstone Galaxy http://i903.photobucket.com/albums/ac23 ... eature.jpg Floor Tile – Enviro Alloy http://i903.photobucket.com/albums/ac23 ... teTile.jpg 2nd Bathroom &Laundry Bench top http://www.laminex.com.au/resource/imag ... _micro.jpg Doors http://www.laminex.com.au/resource/imag ... _cocoa.jpg Floor Tile - Enviro Smoke Kitchen Bench top http://www.qstone.com.au/images/ivory5.jpg Doors http://www.laminex.com.au/resource/imag ... _linea.jpg http://www.formica.com.au/media/swatche ... Shadow.jpg Formica Silver Shadow used for Pot drawers & Kickboards Building in the ***** area of Perth WA Those all look beautiful, especially love the benchtop. Great choices. Building in Seville Grove Perth Floreat by Scott Park Homes Earthworks 16th February Thread https://forum.homeone.com.au/viewtopic.php?f=31&t=24936 Re: Building With SPH - At Scheduling 8Jan 15, 2010 12:57 pm Thanks We looked at the Como & Floreat Plan too, both really nice. Floreat was a little too wide for our block Building the Claremont with SPH viewtopic.php?f=31&t=28206 Earthworks 16/02 Slab 23/02 Drainer 26/02 Bricks 03/03 Brickies started 30/03 Brickie meeting 31/03 Tile meeting booked for 21/06 Paving started 29/07 1st PCI 29/07 2nd PCI 13/08 Handover 09/09 Re: Building With SPH - In Construction 10Jan 15, 2010 3:14 pm Hi tamamontu Another Como Just had a little look at your thread, looking good. How soon to move in day do u think? Building the Claremont with SPH viewtopic.php?f=31&t=28206 Earthworks 16/02 Slab 23/02 Drainer 26/02 Bricks 03/03 Brickies started 30/03 Brickie meeting 31/03 Tile meeting booked for 21/06 Paving started 29/07 1st PCI 29/07 2nd PCI 13/08 Handover 09/09 Re: Building With SPH - More colours 11Jan 20, 2010 1:27 pm Hi peoples Here is our feature and floor tile for our laundry & second bathroom http://i903.photobucket.com/albums/ac23 ... C01285.jpg & Some external colours - Bricks - Geographe Limestone http://www.australbricks.com.au/wa/Prod ... ble-decker Roof - Colorbond Deep Ocean http://www.colorbondcolours.com/go/bsl- ... deep-ocean Gutter/Fascia – C/Bond Mountain Blue Windows - Anotec Dark Grey Front Door – Anotec Dark Grey http://www.boral.com.au/bw/Brendale_col ... site=Boral Garage door - Cedar look Building the Claremont with SPH viewtopic.php?f=31&t=28206 Earthworks 16/02 Slab 23/02 Drainer 26/02 Bricks 03/03 Brickies started 30/03 Brickie meeting 31/03 Tile meeting booked for 21/06 Paving started 29/07 1st PCI 29/07 2nd PCI 13/08 Handover 09/09 Re: Building With SPH - At Scheduling 12Jan 27, 2010 10:10 pm Hey Bec! I can't believe you packed you plans away Maybe they can email them to you? Re: Building With SPH - At Scheduling 13Jan 27, 2010 10:18 pm Hi Bec We are building in Aubin Grove.. should be moving next month I clicked on the 1st link and it didn't work for me Built with New Generation (Summit Homes) We own land!... with a slab on it! Plus a shell of a house with stuff inside ! Re: Building With SPH - At Scheduling 14Jan 29, 2010 1:20 pm Hi Bec Your colours are beautiful!! We are building "the Floreat" in Harvey through Scott park southwest offic Awaiting final plans which they told me would be completed end of last week early this week so fingers crossed it will be any day!! Look forward to watching your progress!!! Building In Harvey Scott Park Homes Achiever 253 (The Floreat) Block Settled Pre Start Complete Awaiting Final Plans 12th March 2010 Slab Down!!! Re: Building With SPH - At Scheduling 15Jan 29, 2010 6:43 pm [quote="Candylea"]Hi Bec We are building in Aubin Grove.. should be moving next month I clicked on the 1st link and it didn't work for me /quote] I think the link is missing the "f" on pdf. Try this http://www.scottparkhomes.com.au/Homes/ ... orplan.pdf Re: Building With SPH 16Feb 02, 2010 4:56 pm Here is our final plan http://i903.photobucket.com/albums/ac23 ... alPlan.jpg Thanks louib76 Not long now Candylea, u must b so excited Building the Claremont with SPH viewtopic.php?f=31&t=28206 Earthworks 16/02 Slab 23/02 Drainer 26/02 Bricks 03/03 Brickies started 30/03 Brickie meeting 31/03 Tile meeting booked for 21/06 Paving started 29/07 1st PCI 29/07 2nd PCI 13/08 Handover 09/09 Re: Building With SPH - At Scheduling 19Feb 02, 2010 6:52 pm Gorgeous plan Bec! Very roomy feel to it viewtopic.php?f=31&t=22766 - my build thread! Time waits for no man. Unless that man is Chuck Norris. Re: Building With SPH - Earthworks booked for 16th Feb 20Feb 03, 2010 2:36 pm Thanks , and thanks for Desquishing Shell , looks much nicer now lol, not sure why it came out like that Can I ask what everyones opinion is on whether to get an independent builder inspector? Building the Claremont with SPH viewtopic.php?f=31&t=28206 Earthworks 16/02 Slab 23/02 Drainer 26/02 Bricks 03/03 Brickies started 30/03 Brickie meeting 31/03 Tile meeting booked for 21/06 Paving started 29/07 1st PCI 29/07 2nd PCI 13/08 Handover 09/09 I would never build with Fowler homes. I built with them in 2021 and till date maintenance issues are pending. All their existing trades and businesses don't work with… 14 105634 Hi I am wanting some opinions about the build of a steel shed I am going to get one about 4.5 x 2.5 m steel shed and the height will be about 2.3-2.4m high The one I am… 0 14469 1 11015 |