Browse Forums Building A New House Re: Anyone Waiting For Stage 4 & 5 Titles in Sandarra 241Apr 20, 2010 6:05 pm Land: Stage 4 Title Settlement: 22nd April '10 Building: DFH, Hartley Site Start: (Scrape) 3.7.10 Slab Completed: 17.7.10 Frame Completed: 30.7.10 Gutters & Fascia Completed: 3.8.10 Roof Completed:9.8.10 Electrical & Plumbing Completed: 13.8.10 Bricks Completed: 24.8.10 Lock up Stage: 30.8.10 Re: Anyone Waiting For Stage 4 & 5 Titles in Sandarra 242Apr 20, 2010 6:22 pm Site Start - 20th July 2010 Slab Pour - 30th July 2010 Frame Start - 6th August 2010 Roof Tiles - 18th August 2010 Plaster Completed - 6th September 2010 Bricks - 3rd - 20th September 2010 Painting - 4th October 2010 Fitoff Begins - 21st October 2010 Re: Anyone Waiting For Stage 4 & 5 Titles in Sandarra 243Apr 20, 2010 6:26 pm Land: Stage 4 Title Settlement: 22nd April '10 Building: DFH, Hartley Site Start: (Scrape) 3.7.10 Slab Completed: 17.7.10 Frame Completed: 30.7.10 Gutters & Fascia Completed: 3.8.10 Roof Completed:9.8.10 Electrical & Plumbing Completed: 13.8.10 Bricks Completed: 24.8.10 Lock up Stage: 30.8.10 Re: Anyone Waiting For Stage 4 & 5 Titles in Sandarra 244Apr 20, 2010 7:58 pm Our Build - Places Fairhaven 23+ - https://forum.homeone.com.au/viewtopic.php?f=31&t=28045 Our Landscaping - Belial's Backyard - https://forum.homeone.com.au/viewtopic.php?f=19&t=45375 Re: Anyone Waiting For Stage 4 & 5 Titles in Sandarra 245Apr 22, 2010 11:56 am Our Build - Places Fairhaven 23+ - https://forum.homeone.com.au/viewtopic.php?f=31&t=28045 Our Landscaping - Belial's Backyard - https://forum.homeone.com.au/viewtopic.php?f=19&t=45375 SANDARRA STAGE 4 TITLED 22/4/10 NOT LONG TO GO STAGE 5 246Apr 22, 2010 4:01 pm Land: Stage 4 Title Settlement: 22nd April '10 Building: DFH, Hartley Site Start: (Scrape) 3.7.10 Slab Completed: 17.7.10 Frame Completed: 30.7.10 Gutters & Fascia Completed: 3.8.10 Roof Completed:9.8.10 Electrical & Plumbing Completed: 13.8.10 Bricks Completed: 24.8.10 Lock up Stage: 30.8.10 Re: SANDARRA STAGE 4 TITLED 22/4/10 NOT LONG TO GO STAGE 5 247Apr 22, 2010 4:07 pm Our Build - Places Fairhaven 23+ - https://forum.homeone.com.au/viewtopic.php?f=31&t=28045 Our Landscaping - Belial's Backyard - https://forum.homeone.com.au/viewtopic.php?f=19&t=45375 Re: SANDARRA STAGE 4 TITLED 22/4/10!!! NOT LONG TO GO STAGE 248Apr 22, 2010 4:10 pm Land: Stage 4 Title Settlement: 22nd April '10 Building: DFH, Hartley Site Start: (Scrape) 3.7.10 Slab Completed: 17.7.10 Frame Completed: 30.7.10 Gutters & Fascia Completed: 3.8.10 Roof Completed:9.8.10 Electrical & Plumbing Completed: 13.8.10 Bricks Completed: 24.8.10 Lock up Stage: 30.8.10 Re: SANDARRA STAGE 4 TITLED 22/4/10!!! NOT LONG TO GO STAGE 249Apr 22, 2010 4:16 pm Our Build - Places Fairhaven 23+ - https://forum.homeone.com.au/viewtopic.php?f=31&t=28045 Our Landscaping - Belial's Backyard - https://forum.homeone.com.au/viewtopic.php?f=19&t=45375 Re: SANDARRA STAGE 4 TITLED 22/4/10!!! NOT LONG TO GO STAGE 250Apr 22, 2010 7:34 pm Site Start - 20th July 2010 Slab Pour - 30th July 2010 Frame Start - 6th August 2010 Roof Tiles - 18th August 2010 Plaster Completed - 6th September 2010 Bricks - 3rd - 20th September 2010 Painting - 4th October 2010 Fitoff Begins - 21st October 2010 Re: SANDARRA STAGE 4 TITLED 22/4/10!!! NOT LONG TO GO STAGE 253Apr 22, 2010 9:16 pm I just hope settlement happens real quick..... Land: Stage 4 Title Settlement: 22nd April '10 Building: DFH, Hartley Site Start: (Scrape) 3.7.10 Slab Completed: 17.7.10 Frame Completed: 30.7.10 Gutters & Fascia Completed: 3.8.10 Roof Completed:9.8.10 Electrical & Plumbing Completed: 13.8.10 Bricks Completed: 24.8.10 Lock up Stage: 30.8.10 Re: SANDARRA STAGE 4 TITLED 22/4/10!!! NOT LONG TO GO STAGE 254Apr 22, 2010 9:53 pm Johno I just hope settlement happens real quick..... You wouldn't think it would take that long.... surely not more than 3-5 working days right? Site Start - 20th July 2010 Slab Pour - 30th July 2010 Frame Start - 6th August 2010 Roof Tiles - 18th August 2010 Plaster Completed - 6th September 2010 Bricks - 3rd - 20th September 2010 Painting - 4th October 2010 Fitoff Begins - 21st October 2010 Re: SANDARRA STAGE 4 TITLED 22/4/10!!! NOT LONG TO GO STAGE 255Apr 23, 2010 4:29 pm Drove over that speed hump where the parklands are!! I have to add, its Smooth as Silk now.. no more hard bangs in my car lol Land: Stage 4 Title Settlement: 22nd April '10 Building: DFH, Hartley Site Start: (Scrape) 3.7.10 Slab Completed: 17.7.10 Frame Completed: 30.7.10 Gutters & Fascia Completed: 3.8.10 Roof Completed:9.8.10 Electrical & Plumbing Completed: 13.8.10 Bricks Completed: 24.8.10 Lock up Stage: 30.8.10 Re: SANDARRA STAGE 4 TITLED 22/4/10!!! NOT LONG TO GO STAGE 256Apr 23, 2010 4:36 pm I walked over them last night, it does meet up nicely. I wonder if they're going to move the temp fencing again to block off stage 5 or whether it will just be left where it is until we title? Our Build - Places Fairhaven 23+ - https://forum.homeone.com.au/viewtopic.php?f=31&t=28045 Our Landscaping - Belial's Backyard - https://forum.homeone.com.au/viewtopic.php?f=19&t=45375 Re: SANDARRA STAGE 4 TITLED 22/4/10!!! NOT LONG TO GO STAGE 258Apr 23, 2010 5:31 pm Nah mate way earlier than that. And was all on me lonesum. Our Build - Places Fairhaven 23+ - https://forum.homeone.com.au/viewtopic.php?f=31&t=28045 Our Landscaping - Belial's Backyard - https://forum.homeone.com.au/viewtopic.php?f=19&t=45375 Re: SANDARRA STAGE 4 TITLED 22/4/10!!! NOT LONG TO GO STAGE 259Apr 23, 2010 5:36 pm That temp fence is anoying now!! cant get to my titled block hehehe Land: Stage 4 Title Settlement: 22nd April '10 Building: DFH, Hartley Site Start: (Scrape) 3.7.10 Slab Completed: 17.7.10 Frame Completed: 30.7.10 Gutters & Fascia Completed: 3.8.10 Roof Completed:9.8.10 Electrical & Plumbing Completed: 13.8.10 Bricks Completed: 24.8.10 Lock up Stage: 30.8.10 You should check your detail drawings, it may show downpipe within brick pier. 14 14307 |