We built with Redink Homes in Helena Valley WA, and wanted to share with you the birth of our first home! Construction started in late October of 2009 and handover occurred 6 months later in April 2010. The builder was fantastic and really took care of us, and I would recommend them without hesitation.
♥ vundaful.blogspot.com ♥
Progress:
- Settlement: June 2009
- Prestart: August
- Slab Down: Oct 25th
- Brickwork: Started Nov 6th, finished Nov 27th
- Roof Beams: Delivered Dec 6th, completed by 12th
- Roof Tiles: Delivered 8th Jan, started 20th, completed by 29th
- Plaster Float: Started 29th Jan, finished 1st Feb
- Ceilings: 5th Feb
- Windows & Sliding doors: 5th Feb
- Plaster (White): Started 10th Feb, finished 12th Feb
- Internal Doors: 15th Feb
- Front Doors (Lock Up): 16th Feb
- Cabinets: 17th Feb
- Sinks and Baths: 18th Feb
- Tiling: Prep 25th Feb, finished 1st March
- Plumbing & Electrical: 8th - 12th March
- Driveway/Alfresco Paving: Pavers delivered 24th Feb, started 16th March, finished 18th March.
- External Painting: 15th March
- Practical Completion Inspection (PCI): 25th March
- Garage Door: 27th March
- Shower Screens/Mirrors: 6th April
- Handover: 9th April
Overview:
- Plan Base: Crimson Living
- House Size: 4 bed / 2 bath
- Exterior: Mexi Cream (Midland Brick)
- Elevation: Face brick and render with cedar-clad gable
- Roof: Clay tile in 'Aniseed' (Bristile's WA-based 'Valley Collection')
- Plans: