Browse Forums Building A New House Re: The Vardy's House - Masterton Crystal MK3 363Jan 31, 2011 7:21 pm Building the Crystal in Wollongong NSW 26th Sept 09 - Paid $2500 1st May 10 - Slab poured 14th May 10 - Frame complete 8th June 10 - Roof complete 21st June 10 - Bricks complete 30th June 10 - Lock Up 6th August - PCI 18th August - Handover Our building thread - https://forum.homeone.com.au/viewtopic.php?f=31&t=27639 Re: The Vardy's House - Masterton Crystal MK3 364Mar 05, 2011 2:18 pm Building the Crystal in Wollongong NSW 26th Sept 09 - Paid $2500 1st May 10 - Slab poured 14th May 10 - Frame complete 8th June 10 - Roof complete 21st June 10 - Bricks complete 30th June 10 - Lock Up 6th August - PCI 18th August - Handover Our building thread - https://forum.homeone.com.au/viewtopic.php?f=31&t=27639 Re: The Vardy's House - Masterton Crystal MK3 365Mar 07, 2011 9:03 am contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: The Vardy's House - Masterton Crystal MK3 366Mar 07, 2011 9:17 am Forrester 43sq We have our keys (3/6/11) Now it's time to decorate (that's the fun part.lol) https://forum.homeone.com.au/viewtopic.php?f=31&t=37598 Re: The Vardy's House - Masterton Crystal MK3 367Mar 13, 2011 11:51 am _______________________________________________________________ We're a knockdown | rebuild ~ Melb SE burbs Building modified version of the Fairhaven Glenaire Homeone thread: viewtopic.php?f=31&t=28429 _______________________________________________________________ Re: The Vardy's House - Masterton Crystal MK3 368Mar 14, 2011 5:59 pm Deemaree Kyndylan Capers: viewtopic.php?f=36&t=46852 My blog: http://www.sufficientlysufficient.blogspot.com/ Re: The Vardy's House - Masterton Crystal MK3 369Mar 17, 2011 3:35 pm Building the Crystal in Wollongong NSW 26th Sept 09 - Paid $2500 1st May 10 - Slab poured 14th May 10 - Frame complete 8th June 10 - Roof complete 21st June 10 - Bricks complete 30th June 10 - Lock Up 6th August - PCI 18th August - Handover Our building thread - https://forum.homeone.com.au/viewtopic.php?f=31&t=27639 Re: The Vardy's House - Masterton Crystal MK3 370Mar 17, 2011 3:45 pm contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: The Vardy's House - Masterton Crystal MK3 371Mar 17, 2011 3:47 pm For info on our build: viewtopic.php?f=31&t=43093 Built the McLaren by Dechellis - slab down 22 Feb - handover 30 Aug 2011 - and gardens finished 9 Dec 2012!! Re: The Vardy's House - Masterton Crystal MK3 372Mar 17, 2011 5:16 pm Gorgeous! SunshineT's Build: viewtopic.php?f=31&t=34585 Designs start: 4/12/09 DA: 5/7/11 Demo: 22/12/11 Slab: 24/2/12 Keys: 31/8/12 4 16705 You’re on the right track, wire brush in a grinder then a zinc rich epoxy primer then a top coat of some sort, like a waterproofing membrane. Raising the concrete would… 1 7020 How good is Simeon?! Always taking time to help others out! Wish we were building in NSW and could work together. Thanks for all that you do! 7 6550 |