Browse Forums Building A New House Re: from council stamp to site scrape..how long? 3Nov 10, 2009 6:58 pm ... built a Promenade with Clarendon. viewtopic.php?f=31&t=25104 20-10-09 - excavation and piering completed ... 12-04-10 - Basins fixed. Connecting to the electrical grid 23-04-10 - PCI 07-05-10 - HANDOVER! Re: from council stamp to site scrape..how long? 4Nov 10, 2009 7:25 pm Similar to ebyelyakov.... Council approval 13th July, then everything went to the bank they issued ACC on 23rd July, Site start for us was to be within 20 days (business days) of the builder receiving the ACC... we had our site scrape on 21 August. Hopefully not long for you now frogger! Even if it's not being sub-divided and you want to keep it as Torrens title, you will still need to talk to a town planner or Council themselves, to see if they will allow… 1 10791 We've had the offer of a short term tenant whilst waiting for CDC/DA home approval and demolition for our knock down rebuild. It would achieve a pretty low rent as it's… 0 13690 This was on google. Development controls 2.3.1 Front setback D1 New buildings within residential areas shall adhere to a front building line, which is 5.5-6m to the… 1 3594 |