Browse Forums Building A New House Re: How’s Holroyd Council for DA? 2Oct 24, 2009 10:45 am ... built a Promenade with Clarendon. viewtopic.php?f=31&t=25104 20-10-09 - excavation and piering completed ... 12-04-10 - Basins fixed. Connecting to the electrical grid 23-04-10 - PCI 07-05-10 - HANDOVER! Re: How’s Holroyd Council for DA? 4Oct 26, 2009 8:42 am ... built a Promenade with Clarendon. viewtopic.php?f=31&t=25104 20-10-09 - excavation and piering completed ... 12-04-10 - Basins fixed. Connecting to the electrical grid 23-04-10 - PCI 07-05-10 - HANDOVER! Re: How’s Holroyd Council for DA? 6Nov 11, 2009 5:36 pm ... built a Promenade with Clarendon. viewtopic.php?f=31&t=25104 20-10-09 - excavation and piering completed ... 12-04-10 - Basins fixed. Connecting to the electrical grid 23-04-10 - PCI 07-05-10 - HANDOVER! Re: How’s Holroyd Council for DA? 9Nov 13, 2009 12:10 pm ... built a Promenade with Clarendon. viewtopic.php?f=31&t=25104 20-10-09 - excavation and piering completed ... 12-04-10 - Basins fixed. Connecting to the electrical grid 23-04-10 - PCI 07-05-10 - HANDOVER! Re: How’s Holroyd Council for DA? 11Jan 21, 2010 8:56 pm ... built a Promenade with Clarendon. viewtopic.php?f=31&t=25104 20-10-09 - excavation and piering completed ... 12-04-10 - Basins fixed. Connecting to the electrical grid 23-04-10 - PCI 07-05-10 - HANDOVER! Re: How’s Holroyd Council for DA? 12Apr 20, 2010 2:03 pm ebyelyakov Welcome to Stockland -- I'm building there as well. My documents were at the Council in March. I also had a pre-DA meeting with one of the city planners (it is advised on their website), however should say it was not much of a help. In May the Council returned the application listing missing/wrong parts. In June in went back to them and mid-July the DA was granted alongside with an additional list of improvements (have no idea why they did not list everything at the first time). Also, the Council showed a level of flexibility allowing me to extend the 1.8 metre part of the fence (we have a corner block) closer to the front line -- about 3 metres more than was specified in building guidelines. However, this was possible to achieve thanks to Tara from Stockland, who wrote a support letter to the Council. Good luck and have fun ps. What probably is worth mentioning that I did not want to have any of the Stockland's default builders and to contribute to development of "a Provincial Village" so I engaged with Clarendon and my home is the first Clarendon in that area. As you can imagine, the first experience is always not the most efficient -- I'm sure that builders experienced with the Estate (like Provincial) should be able to achieve DA from the first try. sorry - but there are 2 houses already in the area which were built by clarendon already... i was looking at pemulwuy. I am just worried about the guidelines. Even if it's not being sub-divided and you want to keep it as Torrens title, you will still need to talk to a town planner or Council themselves, to see if they will allow… 1 6843 We've had the offer of a short term tenant whilst waiting for CDC/DA home approval and demolition for our knock down rebuild. It would achieve a pretty low rent as it's… 0 9913 This was on google. Development controls 2.3.1 Front setback D1 New buildings within residential areas shall adhere to a front building line, which is 5.5-6m to the… 1 2716 |