Browse Forums Building A New House 1 Oct 22, 2009 8:20 pm Hey everyone, Just wondering what your experiences have been in terms of how long did the builders wait before doing anymore work after the slab was done? Thanks Re: How long until any work is done after slab is laid? 2Oct 22, 2009 8:22 pm Our frame started 2-3 days after the slab was poured. Some builders are a bit slower, it might depend on availability of tradies. Re: How long until any work is done after slab is laid? 3Oct 22, 2009 8:29 pm Welcome lv 64000$ question, but after 7days for heavy stuff like bobcats. Where you are coming from is where you are going to... Re: How long until any work is done after slab is laid? 4Oct 23, 2009 8:04 am Our frame started going up two weeks after the slab was laid. 1) I had requested R6 ceiling insualtion batts, however I noticed that on some areas there are huge gaps which will allow hot air to sweep in, and also noticed black/grey… 0 3604 of course there are legal avenues. You've already mentioned it. Sue them. I find it odd that lawyers wouldnt be willing to take on the case, given CCT evidence and… 1 23787 Depends what you're current inclusions are, but we're not including wardrobes and will just use second hand ones until we can save later on to get them built. Also have a… 3 11648 |