For 1J purchaser:
Just received the email from Somerfield:
We have been advised by the Project Engineers of a delay with the Water Authority which is unfortunately holding up compliance for Stage 1J. We are further advised the Project Engineers are meeting with the Water Authority working to resolve this as quickly as possible.
The process from here is as follows;
· Once compliance is received documents will be lodged with Council for approval
· The plan will then be lodged with the Titles Office for registration which can take 10 - 30 working days
· Settlements to take place 14 days from registration of title
Based upon this information, we expect to receive compliance for Stage 1J by end of November and therefore anticipate settlements can take place early to mid December.
We apologise for any inconvenience this has caused, unfortunately this delay has been out of our control.
Please feel free to contact us if you have any questions in relation to getting to settlement.
More delay! Hate it!