Browse Forums Building A New House Re: Receiving the contract and signing straight away?? 2Sep 18, 2009 5:25 pm viewtopic.php?f=31&t=22766 - my build thread! Time waits for no man. Unless that man is Chuck Norris. Re: Receiving the contract and signing straight away?? 5Sep 18, 2009 6:08 pm 12 March 2010 - Land titles received 3 April 2010 - Signed building contract 14 April 2010 - Prestart 28 April 2010 - Loan approved 30 June 2010 - Slab completed 27 August 2010 - Brickwork completed 22 September 2010 - Roofing completed 30 September 2010 - Internal walls plastered 12 October 2010 - Lock Up 19 November 2010 - PCI 26 November 2010 - Handover 29 December 2010 - Moved In https://forum.homeone.com.au/viewtopic.php?f=31&t=32584 Re: Receiving the contract and signing straight away?? 6Sep 18, 2009 6:10 pm Blog: http://bluemistkids.blogspot.com "Never be afraid to try something new. Remember, amateurs built the ark, and professionals built the Titanic." Re: Receiving the contract and signing straight away?? 7Sep 18, 2009 6:48 pm 'A bottle of wine contains more philosophy than all the books in the world.' Louis Pasteur Vegie garden: viewtopic.php?f=19&t=27637&start=0 My Backyard Adventure Re: Receiving the contract and signing straight away?? 9Sep 18, 2009 8:38 pm Caz & Co ALL MOVED IN!! Now comes all the hard work-decorating.... [b]Blog: http://cazoraz.blogspot.com/ Settling in Thread: viewtopic.php?f=31&t=36993 Re: Receiving the contract and signing straight away?? 10Sep 18, 2009 8:45 pm 'A bottle of wine contains more philosophy than all the books in the world.' Louis Pasteur Vegie garden: viewtopic.php?f=19&t=27637&start=0 My Backyard Adventure Re: Receiving the contract and signing straight away?? 11Sep 18, 2009 8:48 pm Caz & Co ALL MOVED IN!! Now comes all the hard work-decorating.... [b]Blog: http://cazoraz.blogspot.com/ Settling in Thread: viewtopic.php?f=31&t=36993 Re: Receiving the contract and signing straight away?? 13Sep 18, 2009 10:26 pm cazoraz lisanne The default for Vic HIA contract, as per the contract is $250 per week. My builder has it as $250 on mine but it really should be say close to what you are paying in rent currently but good luck on trying to negotiate this! mmmm has anyone managed to negotiate a higher amount? and what tricks did you have to play to get it?? Our builder automatically changed our figure to $400 per week, without us even saying anything to them. Was quiet happy with this! Building Thread viewtopic.php?f=31&t=13002 Site start: 8th July 2009 Handover: 11/12/2009! 5 months total build time. 40 sqs of luxuary...Bliss! I've got a challenge here. Background is the builder has cut too deep for the slab and the slab is now below the very substantial retaining wall. It's failed occupancy… 0 18374 You talk about deletions, are they variations or PS and PC adjustments? pleas list them 1 16542 It seems very clear to me that your contract states that a security account does NOT need to be established so the answer to the builder is NO. If in doubt find a contract… 1 8501 |