Browse Forums Building A New House 1 Sep 08, 2009 7:33 pm Hi All, We are building in the West in Melbourne. We are at lock up and the inside has been plastered and the cornices attached. Our builder doesn't like giving timeframes - but I am not sure what / how it all happens from here... We have our doors delivered.....then I am assuming the cabinets are fitted and then they paint?? Any insight anyone can offer into the process from here on will be great.. Thanks Bec Re: Building process 2Sep 09, 2009 10:41 pm I am not surprised that builders dont give timeframes, cause everyone complains and complains if the timeframes arent met, just read these forums. I am a little ahead of you in the build, but this next process drags, since the start of August, all my kitchen and bathroom cabinets have been installed and one vanity basin, all my skirting and window frames were done and all the doors hung and handles fitted, my tiling was done during this time, that took one tiler 3 weeks, then the electrican came back and put all the power points in, the shower screen/splashback was measured, and thats where I am up to. I apologise for any confusion, but your understanding is correct. We approached our situation differently based on advice from… 11 53212 Thanks very much! And would the landscaper/contractor generally involve the engineer or is that something the client would do? Thanks for your help 2 10026 The most definitive answer to your question James is this taken from the James Hardie Axon Cladding Installation Guide - i just happen to have it… 5 3669 |