I've been stalking H1 for months now, and I must say... WOW!! Such a wealth of information! I've been reading through everyones threads and everyones homes are looking gorgeous. Makes me change my mind about what i've chosen for my own place!
So, I'm building with Aussie Living (division of Ventura). I'm building the 'Sensation'. Its a new one, so no display home unfortunately, which made it quite difficult to picture what it looks like! From what I have seen though, its quite similar to the display home in Madeley, so next time I'm in Perth i do believe i'll be paying a visit to have a sticky beak
I've changed it around quite a bit (moved the kitchen, put the garage at the back). I will attempt to attach the plans and a piccy of my block soon!
Has been a bit of a wait!! I went through a broker (something that i won't be recommending to any of my friends...) and applied for the loan at the beginning of May. Unconditional approval was received on the 23rd July and settlement finally went through on the 27 August!! So i now own my block of dirt
I've already had my pre-start, and signed all the final building contracts. So now i'm at a bit of a loss as to what happens next!!
Can't wait for it to progress
PLAN!!!
Changes to the original plan:
The kitchen used to be in that corner *living* area, i've made the pantry into a larger corner pantry and added a bench. Moved the garage to the rear of the property so its now behind the theatre/lounge area. Moved main bedroom window from side of to front of room. Can't think of anything else i really changed...
But there you have it!! My plan
UPDATED TIME LINE
Unconditional Approval: 23 July 2009
Settlement on Land: 27 August 2009
Site Pegged: 20 September 2009
Tap: 20 September 2009
Site Scrap/Spad: 29 September 2009
Plumbing Pipes (internal): 5 October 2009
Mesh Base: 6 October 2009
SLAB!!!: 7 October 2009
External Pipes: 12 October 2009
Window Frames etc: 14 October 2009
Bricks: 19 October 2009
LOO!!!: 22 October 2009
Bricking Started: 27 October 2009
Bricking Completed: 4 November 2009
Roof Frame Started: 12 November 2009
Roof Frame Finished: 20 November 2009
Gas installation done: 20 November 2009
Water installation done: 24 November 2009
Roof Tiles delivered: 27 November 2009
Roof Tiling started: 2 December 2009
Roof Tiling finished: 7 December 2009
Float Started: 10 December 2009
Float Completed: 11 December 2009
Windows Installed: 11 December 2009
Ceilings installed: 14 December 2009
Cornices installed: 15 December 2009
Silver things on roof: 15 December 2009
Plastering started: 17 December 2009
Plastering finished: 18 December 2009
LOCKED OUT: 21 December 2009
CHRISTMAS BREAK: 23 December 2009 - 11 January 2010
Cabinets installed: 12 January 2010
Bath and sinks in: 13 January 2010
Bathrooms tiled: 14 January 2010
Splashback tiled: 14 January 2010
Shelving and doors installed: 27 January 2010
Ceilings, doors, gutters etc
Painted: 29 January 2010
Pavers delivered: 30 January 2010
Toilets, HWS etc installed: 1 February 2010
External painting finished: 2 February 2010
Plumbing finalised: 2 February 2010
Oven and rangehood installed: 10 February 2010
Ceiling light things installed: 10 February 2010
External powerpoints/switches: 11 February 2010
Insulation installed: 12 February 2010
Internal electrics finalised: 12 February 2010
Door knobs: 15 February 2010
Cleaner: 22 February 2010
Paving installers: 23 February 2010
Roof capping finished: 24 February 2010
Carpets half installed: 24 February 2010
Construction Manager visit: 24 February 2010
Blinds installed: 25 February 2010
PCI: 3 MARCH 2010
HANDOVER: 12 MARCH 2010