Browse Forums Building A New House Re: Timeframe advice 7Aug 23, 2009 10:51 pm Quote: What does your contract say? I would check with your SS to get a rough guide for finishing contract guidelines are rubbish, mine has 15 clauses about why the finishing date can be delayed, like dispute with neighbours, weather, access problems, acts of god, theft, civil unrest, materials being difficult to get, or my favourite anything else beyond our control, i informed my builder 3 weeks ago it was the wrong spa, now they tell me that it will take 3 weeks to get that spa. my question is why wasn't it done 3 weeks ago it would be ready now. Versaloc is a mortarless besser block system that still needs a properly engineered footing. If you just do a 400x200 footing it will fail in time. At 17m long you need it… 1 18240 Hi All, I engaged a tradie to install concrete retaining wall 600-800mm high over 32 meters in Victoria. Sleepers are 200*75*2000 mm installed over 17 steel posts. I… 0 6917 Building Standards; Getting It Right! Don't think they are designed for double brick. WA has a particular way of building and unfortunately that's the way a large amount of sills are finished. 3 7014 |