Hi all,
Our builder (big M) gave us the contracts today with 324 days build time for a single storey 29 squares home. Is this reasonable?? We are very disappointed. Should we be?
Please advise.
Our builder (big M) gave us the contracts today with 324 days build time for a single storey 29 squares home. Is this reasonable?? We are very disappointed. Should we be?
Please advise.
Hi Malik, i thought M3tricon was giving 18 weeks build time for all the new houses check this link
18-Week Build Guarantee
The build time guarantee's are generally only if you make no modifications to the plans and an M class slab is needed. PD do a 20 week one but because my slab needs upgrading and I've added a window ( ) they have added an extra 2.5 weeks
For the record, 153 days in total including weekends, weather and PH's (not including christmas) for a 21 sq house with PD