Browse Forums Building A New House 1 Apr 16, 2009 5:22 pm Should we have received a copy of a report from this inspection, and should we have signed off on it? It was doen over two weeks ago and we have nothing in writing and have not signed off on anything Re: Practical Completion Inspection 2Apr 17, 2009 9:57 am Our builder uses a carbon pad where we get one of the three copies, we signed that what was on it was correct and then we signed again once completed. l would say you def should get a copy you need to know that they are going to complete what you've asked strange they haven't given you one! The HIA contract, in the term & conditions section states that "Commencment" is deemed when the drainage is started or the piers are dug or the slab is formed up (incase… 2 6175 Like I said the Occupancy Certificate is not the tollgate that marks the completion of the house. The contract defines… 7 10720 i would suggest nothing is unreasonable for PCI. we did all sorts, including checking the hot water, checking all the GPO's had power, testing that the showers were… 9 98679 |