Hi Everyone
Well we have just received the contract from the Builder which is the standard HIA one with 145 working days (two storey house) and damages if they go over, however in the Special Conditions they have put the following clause:
"the builder can claim an extension of time for the following situation "Delay in availability of material supplies or suitably qualified tradespeople".
Now to me that seems like an open book to extend the build time for as long as they want without incurring damages on the builders part
Has anyone else experienced a similar clause or think that it is a little unreasonable??
Feedback from anyone is most appreciated.
Thanks everyone.