We chose Oracle platinum home a little over 6 months ago to build on a piece of land. We had an anticipated start date of late July but due to DA delay we missed the 4 week grace period by a couple of weeks (I would argue it's been a total mess of council approval etc).
Anyway we get an email asking for 42k because that's the cost of delay (on a 300k home) with no explanation of what is costing that much for the delay. No phone call or anything, just asking is this expected behaviour or should I be worried they either want to cancel the contract or that they might be having money problems?