Anyone feel the same with us?
Delay again and again - Featherbrook Point Cook
Page 1 of 2
Anyone feel the same with us?
Finally settled on august 12th 2008.
I bought in May 2008, settlement scheduled for September 2008.
and then December 2008, and then February 2009 and then April 2009.
Still waiting noww....
:evil: Just got the news from Featherbrook (Central Equity) - our land delayed again for title. We supposed to get our land in Nov 2008 according to the sales person. Then postponed to Jan 09, again to March 09 and now to June 2009. We are so unhappy with it.
Anyone feel the same with us?
Anyone feel the same with us?
Which stage is your land in?
:evil: Just got the news from Featherbrook (Central Equity) - our land delayed again for title. We supposed to get our land in Nov 2008 according to the sales person. Then postponed to Jan 09, again to March 09 and now to June 2009. We are so unhappy with it.
Anyone feel the same with us?
Anyone feel the same with us?
Hi we also purchased a land in Featherbrook and we are in stage 13. Do you mind if you can let me know which stage are you in? stage 13 is supposed to be titled in around july 2009.
As we are first home buyers and to qualify for the $26k first home buyer grant, our house needs to be built within 26 weeks after we sign the builder contract (in May 2009). Does anyone know if our land is late and won't be titled until end of the year, does it mean that we are not qualified for the $26k??
Same situation here
I bought in May 2008, settlement scheduled for September 2008.
and then December 2008, and then February 2009 and then April 2009.
Still waiting noww....
I bought in May 2008, settlement scheduled for September 2008.
and then December 2008, and then February 2009 and then April 2009.
Still waiting noww....
Watch out - we have been told stage one has been delayed again...
Anyone knows - Why the land developer needs a few months for sorting out the sewerage problem (reason given for this time delaying)? Can't they get the thing done quickly?
Could be due to the amount of rock in the ground
As we are first home buyers and to qualify for the $26k first home buyer grant, our house needs to be built within 26 weeks after we sign the builder contract (in May 2009). Does anyone know if our land is late and won't be titled until end of the year, does it mean that we are not qualified for the $26k??
Hi Kikin,
I'm in a very similar situation as you. My land settlement date keeps getting pushed back, and I'm afraid to sign our building contract now just in case the settlement gets pushed back even more, and we need to build within 26 weeks. I gave the SRO a call, and they told me that if you dont build within the 26 weeks, you can apply for an extention. However, every case is looked at as a case by case scenario and you have to prove that the delays were not your fault and it was not foreseenable. I asked them whether i would still be eligible for the grant if the land settlement is delayed, and they couldnt guarantee that i would.
So the best thing is, push your building contract signing date as long as you can, better safe than sorry.
Were looking to build at the moment and that will definably be the case, unless we get in before the FHOG runs out we will walk away.
So on that front, they have a huge need to get it completed before then and sold.
Not sure of the exact issue but there's slope, a golf course and a little creek so it was complex for some reason, but once it was sorted both stages became available quite quickly.
My point is, try to find out what the delay is. If it's just slow development, chances are all the stages will be slow. But if there is a specific issue, once that issue is sorted, the whole process can speed up for subsequent stages.
Do a bit of snooping.
What does that mean?
Does that mean settlement will be coming soon?
Mine is Stage 13.
we recently got the letter about civil works being done in September as well. it also said to make sure our legal and finance matters were in order so we think that means it is genuinely getting closer.
we've seen that the roads are almost completed near our street and the wetlands are being shaped.
I think it's likely we'll get title in September/October.
fingers crossed!
Related
10/06/2023
0
Hi, My home construction is complete, and the handover is scheduled next week. However the construction has been delayed and I have raised this to the builder. The…
26/03/2024
1
So, did they give you a reason? Weather? Slab not poured??