Hello everyone
I am really disappointed at with PD.
The site scrape happened on 27/10 and its fourth week now and
they have not even managed to start the slab as yet. We are at 4th week now. If this is the start, i really wonder how will they manage the whole build.
This week, mon and tues the whether was all good and they have not done anything, i doubt anything will be done for rest of the week due to high chances of rain.
Has anyone else (especially PD) clients faced this delay at the very start.
If yes, do they manage to catch up later on at all... i am stressing out now as i am not ready for nasty surprises related to delays.