Hi Everyone,
I wanted to get some advice.
I am building a custom home and have gotten tenders from a several builders. The latest one (from my preferred builder) says the tender is subject to product / material increase, and if there is an increase in price for any material or product specified the increased amount will be charged, but that there will not be an increase in the builders margin. I called to check if this only applied up until we signed a contract, and was advised, no it applies even after the contract is signed.
They use the HIA NSW contract.
I thought contracts were fixed price contracts, and whilst I'd appreciate that any increases in builders cost prior to signing of the contract would amend the tender, once the contract was signed, it was a fixed price other than if I change something, or spend more than a pc allowance, or hidden site costs for something unforeseen on the site (ie rock) meant more site works.
Correct me please if I am wrong, but I'm not sure what to do and would appreciate any advice you may have.