Browse Forums Building A New House 1 Sep 28, 2024 8:13 pm Hello !! I am currently building a new double storey home in Qld and I want to know more about non compliant framing stage and in the certifer report it says works cannot proceed until defects are rectified. Builder has started to proceed with enclosure stage. I have asked certifer for form 16 and they advised they have not passed inspection so no form 16 can be sent. And advised no work is allowed until defects are done. Just want to know why the builder has decided to go ahead with this when certifer has advised not to proceed? Do all builders do this? Are they allowed to do this? Re: Framing stage non compliant - builder continue work 2Oct 01, 2024 4:00 pm Huynhm3 Hello !! I am currently building a new double storey home in Qld and I want to know more about non compliant framing stage and in the certifer report it says works cannot proceed until defects are rectified. Builder has started to proceed with enclosure stage. I have asked certifer for form 16 and they advised they have not passed inspection so no form 16 can be sent. And advised no work is allowed until defects are done. Just want to know why the builder has decided to go ahead with this when certifer has advised not to proceed? Do all builders do this? Are they allowed to do this? This is a really good question. It really depends on what the defective frame items are and what work the builder is proceeding with. For instance if the inspection has picked up missing joist hangers and other internal items, it would be reasonable for the builder to continue with external works whilst he waits for the carpenters to return so he can keep your build moving. Also depending on how bad the defects are and what they are, he could also possibly continue with rough ins. However if he had started gyprocking then that would be an issue. I hope this makes sense Cheers Simeon Architectural Homes & Duplexes - specialising in custom designing homes to your budget Get a Free Onsite Consultation Today or send a PM for information, questions or advice. Re: Framing stage non compliant - builder continue work 3Oct 01, 2024 5:00 pm Ashington Homes Huynhm3 Hello !! I am currently building a new double storey home in Qld and I want to know more about non compliant framing stage and in the certifer report it says works cannot proceed until defects are rectified. Builder has started to proceed with enclosure stage. I have asked certifer for form 16 and they advised they have not passed inspection so no form 16 can be sent. And advised no work is allowed until defects are done. Just want to know why the builder has decided to go ahead with this when certifer has advised not to proceed? Do all builders do this? Are they allowed to do this? This is a really good question. It really depends on what the defective frame items are and what work the builder is proceeding with. For instance if the inspection has picked up missing joist hangers and other internal items, it would be reasonable for the builder to continue with external works whilst he waits for the carpenters to return so he can keep your build moving. Also depending on how bad the defects are and what they are, he could also possibly continue with rough ins. However if he had started gyprocking then that would be an issue. I hope this makes sense Cheers Simeon Thanks Simeon, What if we have frames overhang. He is starting t insulate the whole house and finish cladding this week. Re: Framing stage non compliant - builder continue work 5Oct 02, 2024 5:59 am Huynhm3 Ashington Homes Huynhm3 Hello !! I am currently building a new double storey home in Qld and I want to know more about non compliant framing stage and in the certifer report it says works cannot proceed until defects are rectified. Builder has started to proceed with enclosure stage. I have asked certifer for form 16 and they advised they have not passed inspection so no form 16 can be sent. And advised no work is allowed until defects are done. Just want to know why the builder has decided to go ahead with this when certifer has advised not to proceed? Do all builders do this? Are they allowed to do this? This is a really good question. It really depends on what the defective frame items are and what work the builder is proceeding with. For instance if the inspection has picked up missing joist hangers and other internal items, it would be reasonable for the builder to continue with external works whilst he waits for the carpenters to return so he can keep your build moving. Also depending on how bad the defects are and what they are, he could also possibly continue with rough ins. However if he had started gyprocking then that would be an issue. I hope this makes sense Cheers Simeon Thanks Simeon, What if we have frames overhang. He is starting t insulate the whole house and finish cladding this week. yeah I would definitely put that in the category of work needing rectification prior to continuing. How bad is the overhang? any chance you can post the relevant sections of the report? Architectural Homes & Duplexes - specialising in custom designing homes to your budget Get a Free Onsite Consultation Today or send a PM for information, questions or advice. Re: Framing stage non compliant - builder continue work 7Oct 02, 2024 7:55 am Ashington Homes Huynhm3 Ashington Homes This is a really good question. It really depends on what the defective frame items are and what work the builder is proceeding with. For instance if the inspection has picked up missing joist hangers and other internal items, it would be reasonable for the builder to continue with external works whilst he waits for the carpenters to return so he can keep your build moving. Also depending on how bad the defects are and what they are, he could also possibly continue with rough ins. However if he had started gyprocking then that would be an issue. I hope this makes sense Cheers Simeon Thanks Simeon, What if we have frames overhang. He is starting t insulate the whole house and finish cladding this week. yeah I would definitely put that in the category of work needing rectification prior to continuing. How bad is the overhang? any chance you can post the relevant sections of the report? Yes I can send it to you pm Re: Framing stage non compliant - builder continue work 8Oct 02, 2024 7:42 pm Huynhm3 Hello !! I am currently building a new double storey home in Qld and I want to know more about non compliant framing stage and in the certifer report it says works cannot proceed until defects are rectified. Builder has started to proceed with enclosure stage. I have asked certifer for form 16 and they advised they have not passed inspection so no form 16 can be sent. And advised no work is allowed until defects are done. Just want to know why the builder has decided to go ahead with this when certifer has advised not to proceed? Do all builders do this? Are they allowed to do this? After I sent a letter from lawyers asking about defects, two days later a engineered from Sydney have provided form 12 aspect for the frames lol Re: Framing stage non compliant - builder continue work 9Oct 03, 2024 5:29 am So I have read the relevant sections of this report, and what worries me the most are the rectification works which are needed to that steel beam. Frame overhangs are not to be ignored but the fixes are simple, I don't know why your builder just doesn't do the work. So if I was in your shoes, I would get my own engineer to inspect and get a second opinion, and then you have two choices: 1. Get your lawyer to fight like hell to get the work fixed 2. Get your own boys in on the weekend to fix both items ( this would be cheaper) All the best Simeon Architectural Homes & Duplexes - specialising in custom designing homes to your budget Get a Free Onsite Consultation Today or send a PM for information, questions or advice. Building Standards; Getting It Right! Hi, yes, we have the report. The builder has rectified the items on the report and we’re moving forward with the build. Thanks for reaching out 2 13827 Building Standards; Getting It Right! Long story short, a toilet room is going to back onto our main bedroom and I want to make it close to soundproof. Im going to build two frames (pretty much a room within a… 0 25754 My building rep is an inspector , witness expert and a builder. The services that he is doing for me is helping me with my project and representing me when I need help… 6 20732 |