Browse Forums Building A New House 1 Feb 15, 2024 2:29 pm Is my builder obliged to provide me with plans showing where electrical and plumbling assets are once the building is completed? Re: Electrical and plumbing plans post hand-over? 3Feb 18, 2024 5:55 pm If there have been changes, variations, during construction then the drawings should be revised, the building permit amended and the current, as built drawings given to the owner as part of the variation. Foremost Building Expert in Australia,assisting with building problems/disputes, building stage inspections,pre-contract review advice for peace of mind 200 blogs http://www.buildingexpert.net.au/blog They should be run in the frame, when run on the outside the pipes breach the cavity clearance. Most times the brickies mortar will drop on them and dry creating a… 1 7798 Building Standards; Getting It Right! When my house was built (over 7 years ago), the post brackets were done to allow for concrete porch, but they didn’t allow for the planned stone paving. I’m finally… 0 13118 DIY, Home Maintenance & Repair Hi all, just joined. I had the house reolumbed and going to put in shower base - poly marble that has 50 mm outlet built into the base. The plumbers have 100 mm pipe… 0 10608 |