Browse Forums Building A New House Re: DA vs CDC (Approval Times) in Ku-ring-gai Council? 2Feb 13, 2024 4:38 pm ![]() Hi all, Anyone have experience/knowledge on how long usually either the DA or CDC process it takes for building a new home in the Ku-ring-gai Council area? (Area's such as St Ives, Pymble, Gordon, Kilara)? Thanks in Advance Hi Minho I have heaps of experience in Ku-ring-gai with both DAs and CDC ( this is the main area we build in). DA's are taking 12-18months and CDC's we have been doing in 2-3 months. If you can get your approval via CDC I would highly recommend it. Council is incredibly slow, pedantic and their approval conditions are onerous. All the best Simeon Architectural Homes & Duplexes - specialising in custom designing homes to your budget Get a Free Onsite Consultation Today or send a PM for information, questions or advice. I'm in NSW and am applying CDC for building a retaining wall. The wall only needs to be 800mm at the highest point . I'm thinking just wooden sleepers. 1. For CDC… 0 383 5 11738 ![]() Dear all, Requesting your help in relation to a CDC code. We are building a new home in NSW on a corner lot (500m2, 15m wide) following Greenfield CDC code. Our design… 0 6904 |