DA vs CDC (Approval Times) in Ku-ring-gai Council?

Page 1 of 1
Hi all,

Anyone have experience/knowledge on how long usually either the DA or CDC process it takes for building a new home in the Ku-ring-gai Council area? (Area's such as St Ives, Pymble, Gordon, Kilara)?

Thanks in Advance
minho
Hi all,

Anyone have experience/knowledge on how long usually either the DA or CDC process it takes for building a new home in the Ku-ring-gai Council area? (Area's such as St Ives, Pymble, Gordon, Kilara)?

Thanks in Advance

Hi Minho

I have heaps of experience in Ku-ring-gai with both DAs and CDC ( this is the main area we build in).

DA's are taking 12-18months and CDC's we have been doing in 2-3 months.

If you can get your approval via CDC I would highly recommend it.

Council is incredibly slow, pedantic and their approval conditions are onerous.

All the best


Simeon
Related
30/05/2023
0
Rear setback confusion for NSW CDC Housing Code

Building A New House

Hi All, see above image. The required setback from the rear boundary in my case is 5m, as you can see the shape of the site and location of the boundary is slightly…

12/06/2023
0
Driveway works under a CDC

Renovation + Home Improvement

I want to build a bigger driveway (without a nature strip) than has been approved under my CDC. I’ve also had a DA approved to build a deck. It looks like I can do this…

12/06/2023
0
CDC Housing Code 3: Gross Floor Area vs Floor Area

Building A New House

CDC Housing Code 3 When to apply Floor Area external face of wall vs Gross Floor Area internal face of wall. Reading thru CDC Housing Code 3, lets take a lot 915sqm.…

You are here
Building ForumBuilding A New House
Home
Pros
Forum