Browse Forums Building A New House 1 Sep 09, 2023 4:01 pm Could someone tell me for a bulder to claim extended time and use rain days as their excuse, would this time only apply from slab to the rood on ? Re: rain day calculation 2Sep 10, 2023 9:38 am Scorpiot10 Could someone tell me for a bulder to claim extended time and use rain days as their excuse, would this time only apply from slab to the rood on ? Yes you are correct, unless there are outside works which form part of the contract such as landscaping or driveways, and importantly, the work delayed is on the critical path. Basically, once you have lockup and all external building works are completed such as external walls, paint etc rain delays can not apply, and then you can only apply them to work which is on the critical path. For example, if the driveway is part of the contract, but it rains whilst they are gyprocking, as the driveway is not on the critical path ( generally driveways are done right before handover) they can't legitimately claim a wet weather delay as the rain has not stopped them completing the internal walls ie the critical path work. This can apply to any external works such as balustrading, pool tiling etc which wouldnt be completed until the end. I hope this makes sense, if not let me know Cheers Simeon Architectural Homes & Duplexes - specialising in custom designing homes to your budget Get a Free Onsite Consultation Today or send a PM for information, questions or advice. 4 13824 That was always going to be a challenge and a test of patience. Full marks to your mate. Did you discuss the wet area near the trampoline? 16 36957 The bottom of the downpipe has been taped (see the black tape) to seal the necessary gap between the downpipe and the adaptor that would normally prevent the downpipe… 3 16480 |