I am currently building a Duplex in Ryde Council area with a project builder.
After the electrical appointment, I was quoted additional Temporary Underground Power Services Provisions to 2nd dwellings for around $5K due to the area is under Ausgrid. This cost doesn't include the permanent power connection to the 2nd dwellings upon subdivision approvals.
My questions are below;
Is it normal for builder or electrical company charge us for this temporary power to the 2nd dwellings (It should be ready to move in for all the building cost mentioned in HIA tender)?
What if, I don't want to proceed with them and will I get no power supply to the 2nd dwellings?
What is your experiences in dealing with such situations and any recommendations?
Thanks.
JW.