Hey all,
I hope you are well.
We are reaching the end of our >500days build and at the Pre-handover inspection, the inspector report showed a few bowed cornices and at least 5 door frames out of parallel with the ceiling by a lot more that the Standards allow. They were a lot of other items not built to australian standard or not in line with the contract.
Have anyone experienced these problems? And did you go ahead with the handover? My concern is they will take so long and their workmanship is horrible, I fear they will break more things.
Also even they are over the contracted time, they don`t answer when asked about the compensation.
Regards