Browse Forums Building A New House Re: Building with Chatham Homes - From Contract to Completio 11Aug 28, 2023 9:24 am Timeline: Fenced: March 9, 2022 Piers bored March 14, 2022 Piers concreted March 16, 2022 Preslab plumbing March 21, 2022 Slab cut April 1, 2022 Slab formwork April 9, 2022 Slab poured April 26, 2022 Frame delivered (ground floor put up), May 3, 2022 Steel, May 24th 2022 Second floor May 27th 2022 Trusses 6th June 2022 Roof upper level 28th June 2022 Wall shaving and truing 27th August 2022 Site Manager Change: 13th September 2022 Roof insulation Changed: 3rd October 2022 Two plan scaffolding dropped: 5th October 2022 Ground Floor windows installed and frame defect rectification work starts: 11th November 2022 Bricks Delivered: 25th November (9000 bricks) Brick Setout and moving of bricks 28th-29th November Brick laying commences: 30th November Brick laying was completed early December Bricks washed: 24th Jan Eaves (1st floor) started: 30th January Lower Roof - Early April Site vandalised - Mid April Glazing Complete - Late April Lock up carpenter - Early May New SS - Early June Site Clean - Mid June Frame Sign Off - Late June Lock up carpenter - Early July New SS - Late July Rough ins - Mid July You talk about deletions, are they variations or PS and PC adjustments? pleas list them 1 16809 Like I said the Occupancy Certificate is not the tollgate that marks the completion of the house. The contract defines… 7 10817 I've decided, after a period of confusion (my building broker told me it's probably not worth it to use a lawyer, but others have said it is a must) that I definitely will… 7 28038 |