Can my builder claim an additional amount for a provisional sum at the final payment?
The situation is that at the start of the build in may 2021 not enough soil was removed from the site. We identified this at the PCI in December and the builder has just rectified the site levels and external stormwater plumbing. The builder is now claiming extra money on the final invoice for the additional soil removal. The builder has provided no receipts for the provisional sum