Browse Forums Building A New House 1 Nov 29, 2021 7:13 pm Hi peeps, We are building with Allcastle Homes, and started construction on the 16/08/2021. Slab was laid 27/09/2021. All the frames are on-site and nothing has been done and as of today its the 29/11/2021. How long did it take for you to get from start of construction to frame finish. Because at then moment I'm feeling it's ridiculous of where we are sitting right now. It's taken at least 16 weeks and still nothing. Thanks. **MrzMutton** Building with Allcastle Homes (Big Bannaby 36 Ascot) My Blog: https://andreaandstevesascot36.blogspot.com/ Re: How long from start to frame finish stage? 2Nov 29, 2021 8:46 pm From the first day they touched the site to frames was about 6-7 weeks, most of that time was waiting for the frames and trusses to arrive. The frames were up and finished roughly 3 days after they were delivered. Hi, did you get any money from insurance? if you did, does it match what you've already paid the builders? 3 5000 You paid him in full is a lesson you won't forget dear me 2 8753 Building Standards; Getting It Right! But they didn't even leave it at one level it goes up and down along the whole front of the house 4 7162 |