Hi peeps,
We are building with Allcastle Homes, and started construction on the 16/08/2021. Slab was laid 27/09/2021. All the frames are on-site and nothing has been done and as of today its the 29/11/2021. How long did it take for you to get from start of construction to frame finish. Because at then moment I'm feeling it's ridiculous of where we are sitting right now. It's taken at least 16 weeks and still nothing.
Thanks.
From the first day they touched the site to frames was about 6-7 weeks, most of that time was waiting for the frames and trusses to arrive.

The frames were up and finished roughly 3 days after they were delivered.
Related
18/04/2024
8
Hebel + steel frame vs brick+ timber frame

General Discussion

This is 100% true. You can not hang anything on steel frames. very frustrating

15/04/2024
4
Pro finish tiling group

Renovation + Home Improvement

The wallopers will just say it's a civil matter.

14/01/2024
4
Render finish

Building Standards; Getting It Right!

But they didn't even leave it at one level it goes up and down along the whole front of the house

You are here
Building ForumBuilding A New House
Home
Pros
Forum