How long from start to frame finish stage?
Page 1 of 1
We are building with Allcastle Homes, and started construction on the 16/08/2021. Slab was laid 27/09/2021. All the frames are on-site and nothing has been done and as of today its the 29/11/2021. How long did it take for you to get from start of construction to frame finish. Because at then moment I'm feeling it's ridiculous of where we are sitting right now. It's taken at least 16 weeks and still nothing.
Thanks.
The frames were up and finished roughly 3 days after they were delivered.