Browse Forums Building A New House Re: Are NSW COVID restrictions impacting the build/remedial 3Oct 12, 2021 8:31 am Architectural Homes & Duplexes - specialising in custom designing homes to your budget Get a Free Onsite Consultation Today or send a PM for information, questions or advice. Re: Are NSW COVID restrictions impacting the build/remedial 6Oct 13, 2021 12:27 pm tsunamisukoto I am currently building in regional NSW and I'm having a hard time getting my slab down. I had letter to commence to the builders 12 weeks ago. took them 8 weeks to do site cut/fill/benching. Now its been about another month and still no piers/slab. According to their online portal of milestones, I was meant to have the slab done 2 months ago. I just want my darn homebuilder grant haha I hope you get your piers and slabs down now, as it has been at least few weeks for trades that could return to uninhabited building sites. If its any consolation, it your slab goes down in December, it will cure through the Christmas and January break. regardless, your contract stipulates a payments schedule and SOPA doesn't give provision to that scenario. Your contractual terms appear to stand. Hence get a lawyer, it… 4 11880 If so what were the "special circumstances" under which it was granted? "Note: If the development consent is for 'dual occupancy' an owner-builder permit can only be… 0 14076 Block of two storey townhouses requires painting on the roof. A brick parapet wall separates each unit and extends above the tiled roof. The parapet walls require sealing… 0 3503 |