Browse Forums Building A New House Re: HIA Building contract - clause 19 delays COVID 2Aug 13, 2021 12:59 pm Designer,Engineer (Civil,Const & Envir),Builder,Concrete & Masonry Contract.Struct Repairs Re: HIA Building contract - clause 19 delays COVID 4Aug 18, 2021 7:49 pm Get sound legal advice. We manage Building Disputes, Construction Contracts, Security of Payment. PM for queries. https://www.contractsspecialist.com.au/articles/ Re: HIA Building contract - clause 19 delays COVID 5Aug 18, 2021 7:58 pm Regardless of what the contract says if the builder has delays because of events beyond builder's control it will be reasonable to allow extension of time, if not in contract then in common law. What is the problem? If the builder has just cause and has properly articulated the claim then extension of time will follow. Assume that there is a dispute and goes to VCAT. Vcat will make a decision that is fair taking account of all evidence and even may rectify the contract if it deems fit. Want to litigate? The price of the ticket is steep. Foremost Building Expert in Australia,assisting with building problems/disputes, building stage inspections,pre-contract review advice for peace of mind 200 blogs http://www.buildingexpert.net.au/blog Unless there is something in special conditions the builder does not have to give you timeline. If your demolition contractor has not removed Asbestos and it was found… 12 28811 You talk about deletions, are they variations or PS and PC adjustments? pleas list them 1 16569 10 12322 |