HIA Building contract - clause 19 delays COVID
Page 1 of 1
Specifically they are claiming civil commotion.
Anyone come across this? Got any suggestions as how to approach?
I think it is reasonable for them to claim some extension of time but this clause does not seem appropriate.
The Federal and State governments that have created this problem with the stimulus Home builders grant?
Prices have skyrocketed, trades and materials are in shortage, builders are forcing battlers to wait it out, while some will go bankrupt.... it's going to be a long painful wait for many. Goodluck
Hello, we are building in NSW with Masterton. We signed our contract in 2019 (pre COVID) with the HIA contract edition 8a. Clause 19 is delays and extensions of time and our building is claiming an extension of time under 19.1 (b) an act of God, fire, explosion, earthquake or civil commotion due to not being able to get trades people due to COVID in Sydney.
Specifically they are claiming civil commotion.
Anyone come across this? Got any suggestions as how to approach?
I think it is reasonable for them to claim some extension of time but this clause does not seem appropriate.
Specifically they are claiming civil commotion.
Anyone come across this? Got any suggestions as how to approach?
I think it is reasonable for them to claim some extension of time but this clause does not seem appropriate.
Hi Helentres
This is currently a contentious issue that many projects are experiencing. It is costly to escalate contracts to dispute, especially against large builders such as Masterton. If you look online, you will identify that Masterton is litigious and they have their own in-house lawyers. If you are not wanting to spend a lot of money on costly litigation, then the better option might be to negotiate with Masterton to get certainty as to the completion date.
If you require advice on your question, then it may be best to consult with a building and construction lawyer in Sydney.
Cheers
John Dela Cruz
What is the problem? If the builder has just cause and has properly articulated the claim then extension of time will follow.
Assume that there is a dispute and goes to VCAT. Vcat will make a decision that is fair taking account of all evidence and even may rectify the contract if it deems fit. Want to litigate? The price of the ticket is steep.
Related
19/11/2023
12
Unless there is something in special conditions the builder does not have to give you timeline. If your demolition contractor has not removed Asbestos and it was found…
3/09/2023
1
You talk about deletions, are they variations or PS and PC adjustments? pleas list them