We have been given notice of practical completion, along with final account and tax invoice.
The site supervisor has said that the pre practical completion inspection, handover and practical completion will all take place on the same day. Is this normal?
This is also the second notice, account and tax invoice. Practical completion was meant to be last Friday but builder reneged on the day.
This is what we received:
__________________________________________________________________________________________
NOTICE OF PRACTICAL COMPLETION
In accordance with Clause 21 of the HIA Building Agreement, set out below please find our Notice of Practical Completion.
Practical Completion means: Practical completion means when the building works are complete except for minor omissions and defects that do not prevent the building works from being reasonably capable of being used for their usual purpose.
1) We, the Builder, hereby deem the date of Practical Completion of this Property to be: Friday, 21 May 2021
2) You (The Property Owner/s), are booked to meet your Site Supervisor on site for final handover, on: Friday, 21 May 2021 (Tentative to be confirmed by site Supervisor)
Please Note: The Owner is responsible to insure the building works from the date of Practical Completion. Refer to Clause 38.7 of Contract