As title says. I have PCU coming up on the 4th June and my site supervisor has advised he has done his "Supervisor PCI" and marked out all errors and markups to be fixed which will be rectified by the time we have ours (There was a bit of blue tape through the house.)
My question is what should I be looking for?
I know to be looking for
- Imperfections on walls and roof with paint etc.
- Tapware works and is fitted correctly
- Doors open and close good
- Brickwork chips and imperfections
- Plugs work
- Tile chips and drumminess
- Lights and plugs as per electrical plan (Have done already but will triple check)
- Scratched/broken glass in windows and window paint scratches
- Cavity doors open and close with ease
Any assistance or tips would be greatly appreciated.