Hi all, my partner and I are building our first home, we are almost finished! I sure wish I found this forum months ago. It would have been so helpful.
Our build is nearly finished but the last couple of months the usual order of building hasn't happened. As there was a 5 week delay in painting because of the lack of painters in the area. I'm having trouble working out how long until our build might be completed and all I'm getting from our supervisor is "not long to go".
The inside of the house has been painted, tiling completed, kitchen/bathroom/laundry cabinets installed.
They are doing the laminate and carpets on Thursday and Friday. Painting the outside should be completed this week, weather permitting. They are yet to install the taps, toilets, sinks, lights, switches, all doors including a barn door. I can see a few minor things that will need to be fixed mostly paint. But I want one brick replaced that has a major chip in it on the front of our façade (a tradie most have knocked something into it, wasn't there when the bricks went up)
My boss wants to know when Ill be taking leave for our move. I know its a difficult question to answer but does anyone have an idea of how much longer it could be for us?
Thanks for any insight