Browse Forums Building A New House Re: KDR - Fencing 2Apr 22, 2021 10:57 am Kotex Hi All, Do we need to arrange fences after demolition ? Or is that covered by builder under OHS ? Can we keep the land open after demolition till, builder takes over ? Thanks Hi Kotex Temp fencing is pretty cheap, Just for the frontage you're probably going to spend $150/week. What most demo companies do is to include say 3 months work of fencing which includes the demo period and a a while after. Just ask your demo company cheers Simeon Simeon McGovern Affordable Custom Homes, We design and build to your budget Ashington Homes www.ashingtonhomes.com.au We were lucky in that our old house was so small (86 square metres) compared to the new house, they were able to take enough readings around the old backyard house before… 8 24824 The biggest challenge will be if you take out a loan and then run out of money - you'll have an incomplete security and lenders do not like this so you can get stuck.… 2 13508 Hi, I am looking into doing a KDR in Melbourne and am contemplating using Kialla Homes. I am looking for feedback on them from others who have built with them. 0 8188 |