Browse Forums Building A New House 1 Dec 09, 2020 7:20 am My builder is Metricon. After 5 months, roofs not finished, and bricks not finished. Actually the construction has paused for almost two months. The site manager always told me he is waiting for the roof tradies. Is it normal? Re: Metricon : Roofs and bricks not finished after 5 months 2Dec 29, 2020 11:07 am No. That's really bad. In 3 months with Fowler homes I have Slab, Roof, Bricks and Plumbing rough in all complete. This certainly doesn't look good. I would be engaging with an independent inspector to have a look at this. As for the unscheduled site visits, most builders are quite… 1 21882 I had a similar issue with my fridge not too long ago. It wasn't the same model, but the symptoms were pretty much the same: the compressor would start and then stop… 3 5164 interesting situation what happened after builder issued final invoice? did you list as defect or not does the building surveyor have any responsibility? ie. issuing… 13 39152 |