Browse Forums Building A New House 1 Sep 15, 2020 1:58 pm Hi, Our bank has informed us they will not release final payment to builder until certs of our home have been released by builder. Builder is refusing to hand over certs since we signed practical completion back on 15th June. They are also refusing to hand us over keys to our home. They keep sending us reminder payment emails however. It’s so odd, we want to pay them so this contract can end, however concerning why they are not following government policies. Any advice Re: Certs and final payment 2Sep 15, 2020 2:11 pm ![]() Hi, Our bank has informed us they will not release final payment to builder until certs of our home have been released by builder. Builder is refusing to hand over certs since we signed practical completion back on 15th June. They are also refusing to hand us over keys to our home. They keep sending us reminder payment emails however. It’s so odd, we want to pay them so this contract can end, however concerning why they are not following government policies. Any advice Building Grange 22 by Coral Homes in QLD -> https://forum.homeone.com.au/viewtopic.php?f=31&t=97426&p=1860633#p1860633 Re: Certs and final payment 3Sep 15, 2020 2:14 pm ![]() Hi, Our bank has informed us they will not release final payment to builder until certs of our home have been released by builder. Builder is refusing to hand over certs since we signed practical completion back on 15th June. They are also refusing to hand us over keys to our home. They keep sending us reminder payment emails however. It’s so odd, we want to pay them so this contract can end, however concerning why they are not following government policies. Any advice Building Grange 22 by Coral Homes in QLD -> https://forum.homeone.com.au/viewtopic.php?f=31&t=97426&p=1860633#p1860633 Re: Certs and final payment 4Sep 15, 2020 2:29 pm ![]() ![]() Hi, Our bank has informed us they will not release final payment to builder until certs of our home have been released by builder. Builder is refusing to hand over certs since we signed practical completion back on 15th June. They are also refusing to hand us over keys to our home. They keep sending us reminder payment emails however. It’s so odd, we want to pay them so this contract can end, however concerning why they are not following government policies. Any advice Yes we don’t want the bank to budge. Never heard of a builder wanting to be paid yet won’t send certs. Very concerning hi Norfolk we are not happy with were the quality finishes they did… 4 1203 Thank you- that’s what I am hoping- we have to be out of our rental too but didn’t know how severe St George would be in progressing payment 6 2168 Assuming you have a standard HIA contract with no special clauses about this, it is the builders responsibility to ensure everything including electrical, data and… 4 987 |