Based on our experience, you will receive DEP and Draft Construction Plans first - once signed off you will receive the following which you need to sign off as well:
- EP PCV
- EP
- Construction Plans
- Final accounts
Above took us 2 1/2 weeks. We are now in Production Estimates!!!
As we didn't have a bank loan you will need to provide bank loans and schedules sign off from your bank as well.
Good Luck!
Cool, 2.5 weeks is not too bad, i'm hoping it will be done in a week which is what they were saying but i'm always let down.
We only need bank loan towards the tailend of the build so shouldn't be held up with that as we would just provide upfront payment to them to start.