Browse Forums Building A New House Re: Hawkesbury custom build- we've been slabbed:) 41Sep 27, 2015 3:33 pm Hi caff, any updates in your frames? 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Hawkesbury custom build- we've been slabbed:) 42Sep 27, 2015 10:13 pm This week - fingers crossed 11/11/13- dep paid 4/4/14- settlement Feb '15- DA app 6/8/15- CC site works begin 19/8/15- Formwork 25/8/15- slab 3/9/15- elect. appt 13/10/15 - frame started 19/10- bricks started 31/10 - roof done Re: Hawkesbury custom build- we've been slabbed:) 44Sep 28, 2015 11:12 pm No - nothing today:( This sure is a test of patience. 11/11/13- dep paid 4/4/14- settlement Feb '15- DA app 6/8/15- CC site works begin 19/8/15- Formwork 25/8/15- slab 3/9/15- elect. appt 13/10/15 - frame started 19/10- bricks started 31/10 - roof done Re: Hawkesbury custom build- we've been slabbed:) 45Sep 30, 2015 9:46 pm Hang on there caff. There's no harm giving a little push to their team. Re: Hawkesbury custom build- we've been slabbed:) 47Oct 07, 2015 9:00 pm No- still no frames. We've been advised they'll be delivered next Monday 12th...will wait and see. 11/11/13- dep paid 4/4/14- settlement Feb '15- DA app 6/8/15- CC site works begin 19/8/15- Formwork 25/8/15- slab 3/9/15- elect. appt 13/10/15 - frame started 19/10- bricks started 31/10 - roof done Re: Hawkesbury custom build- we have a frame!! 48Oct 12, 2015 4:56 pm Woohoo! Our frames were delivered today and assembly starts tomorrow:) 11/11/13- dep paid 4/4/14- settlement Feb '15- DA app 6/8/15- CC site works begin 19/8/15- Formwork 25/8/15- slab 3/9/15- elect. appt 13/10/15 - frame started 19/10- bricks started 31/10 - roof done Re: Hawkesbury custom build- we have a frame!! 50Oct 12, 2015 8:06 pm KezHam Yeee haaaa!!! So happy for you Thanks Kezham- we are very excited. 11/11/13- dep paid 4/4/14- settlement Feb '15- DA app 6/8/15- CC site works begin 19/8/15- Formwork 25/8/15- slab 3/9/15- elect. appt 13/10/15 - frame started 19/10- bricks started 31/10 - roof done Re: Hawkesbury custom build- we have a frame!! 51Oct 12, 2015 8:40 pm Glad to see that you have frames, hope it progress to bricks quickly for you. 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Hawkesbury custom build- we have a frame!! 52Oct 13, 2015 8:40 pm 11/11/13- dep paid 4/4/14- settlement Feb '15- DA app 6/8/15- CC site works begin 19/8/15- Formwork 25/8/15- slab 3/9/15- elect. appt 13/10/15 - frame started 19/10- bricks started 31/10 - roof done Re: Hawkesbury custom build- we have a frame!! 54Oct 13, 2015 9:32 pm Nice to see the progress, can't wait to see mine going up. 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Hawkesbury custom build- and now for some bricks:) 56Oct 19, 2015 6:00 pm Brickies started today. Can't believe how quick it is happening now. The bricks are Blue Steel Flash and I LOVE them. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ 11/11/13- dep paid 4/4/14- settlement Feb '15- DA app 6/8/15- CC site works begin 19/8/15- Formwork 25/8/15- slab 3/9/15- elect. appt 13/10/15 - frame started 19/10- bricks started 31/10 - roof done Re: Hawkesbury custom build- and now for some bricks:) 58Oct 19, 2015 8:36 pm Pretty quick, really happy for you. 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Hawkesbury custom build- and now for some bricks:) 59Oct 19, 2015 8:46 pm KezHam Yay so happy things are progressing quickly for you now you are going to catch back up to me in no time at this rate Thanks KezHam, I actually can't believe that this time last week it was just a slab. We went there yesterday to have a good look around and I just sobbed uncontrollably- it was like all the tension, stress and delays exploded out of me. I felt so much better after that:) 11/11/13- dep paid 4/4/14- settlement Feb '15- DA app 6/8/15- CC site works begin 19/8/15- Formwork 25/8/15- slab 3/9/15- elect. appt 13/10/15 - frame started 19/10- bricks started 31/10 - roof done Re: Hawkesbury custom build- and now for some bricks:) 60Oct 19, 2015 8:55 pm I can feel exactly what you are going through at the moment, hope all goes smoothly from now on. 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. I'd get the gutters to match your roof and pipes to match the paint - otherwise they become a feature. Nice pick with the paint colours! 1 35089 6 57368 Soak wells and electrical run in happening this week! Summit has told me they will relocate the laundry plumbing after the walls are completed. I'm actually pretty happy… 13 36876 |