[quote="west_rocks"]Hi Folks,
Did anyone in this forum go via council?.
How much is the realistic turnaround time for a DA/CC through Liverpool Council (not CDC)?.
Reason I ask is am building in EP Village Square through Council due to some design constraints. Would be good to hear from people who have gone via similar process
Thanks!
Did anyone in this forum go via council?.
How much is the realistic turnaround time for a DA/CC through Liverpool Council (not CDC)?.
Reason I ask is am building in EP Village Square through Council due to some design constraints. Would be good to hear from people who have gone via similar process
Thanks!
It took 4 weeks to get our DA approved by Liverpool council.
Thanks AussieIndian. Was that done recently.
Reason I ask is I called their office a few days back and they said processing time these days is minimum 12 weeks.
Perhaps it has become longer since the time you applied?.
I thought they have a fast DA approval in place...
http://www.liverpool.nsw.gov.au/council ... ent-system[/quote]
Nope confirmed am not eligible for fast track process.