I am a bit worried with m. I had my pci late last week and the roof tiler left whilst he was rearranging the roof tiles. We noticed he left one tile off the rood leaving a gap. I checked today and the tile had not been put back on. I r a ng my ss and he said that he will get onto tje tiler and if it needs to be painted it will.
I am worried m or the tiler will just slap on a tiler leaving the dirt or any rain damage.. I hate this as they will just want tell me what I want to hear.
Can I take a ladder there and take photos or fix it myself? ????? M has lost the ball on this one..
Any advice ???
Just take a photo next time you visit the site, if you can, so we know what you mean. You mentioning gap on the roof, then paint and then dirt.
The sub-contractors don't care much if they miss a tile or a nail, but M does. If you find things wrong or not to standard, just tell M and M should chase it up. Just keep asking for a fix.
Most times, once sub-contractors "finished" the job, they are on another job the next day, so it is hassle for them to come back, so they leave it till they are in the area. Sometimes this is too late or can stop some progress.
During our build, any issues I found my SS took care of it within few days. Just that M's office did not like me being on site and kept sending me emails and letters to stay off-site